PORT OF SUAPE INVESTS MORE THAN BRL 600 MILLION IN IMPROVEMENT

The Suape Industrial Port Complex has finished the third phase of the stone jetty’s recovery work, which is crucial for preserving the mooring berths. The overall costs in three phases surpass BRL 611 million and include dredging, lighting upgrade, and fender replacement. The last phase, costing BRL 123 million, will begin in July 2024 to bolster the barrier against sea currents and waves. In the third phase, 1.6 kilometers of the jetty were repaired with stone blocks of varied sizes. Suape’s CEO underlined the necessity of port security and climate change preparations. The project, which began in 2018, is both complicated and expansive.
Source: TV Jornal (*Translated by Ia Niani)